January 28, 2002 Vol. VI, No. 9



Overnight Electrical Shutdowns Scheduled on Campus

Physical Plant Management is assisting DMJM/JGM and the university's electrical engineering firm, P2S Engineering, in disconnecting the 1994 earthquake-era high-voltage feeds to temporary substations and some of the related repairs to the campus electrical high voltage infrastructure.

To accomplish this, the electrical power and all related services, including lighting (interior and exterior), fire/life safety systems, various modes of communication (data, phone, etc.), HVAC, fume hoods, etc., will be off in various areas from midnight (00:01 a.m. on the days/ dates listed below) until 5 a.m. on those mornings.

Campus personnel should turn off all sensitive or non-essential electrical equipment in the affected buildings prior to these electrical outages on the days involved. We apologize for any possible inconvenience this may present, and thank you for your continued patience.

The schedule of overnight outages, subject to change if work is completed earlier, is as follows:

For more information, concerns or questions, call Tom Brown in PPM at x3914, Mike White in PPM at x2236, Ken Rosenthal of DMJM/JGM at x7720, or the PPM Call Center at x2222. For data network and communications information, questions or concerns, call Greg Nicols in ITR at x6230, Jeff Craig in ITR at x4878, or ITR Network Administration at x4700.


@csun | January 28, 2002 issue
Public Relations | University Advancement
Home | CSUN A-Z | New Sites | People Finder | Calendar | News & Events
Students | Faculty/Staff | Parents/Prospective Students | Alumni | Business & Government | The Community