Obtain verbal/email confirmation from the Project Director that:

Clearing of Remaining Purchase Orders

Generate a Project Budget Status report (BBA Report) to ensure that all Purchase Orders (POs) are cleared and there are no outstanding POs.

Payment of Outstanding Expenditures

Ensure that all of the following project expenses have been paid:

Completion of Invoicing

Generate an AR Report (Accounts 120110 - 120170) for the project to determine if the granting agency still needs to be invoiced and if all invoices billed have been received.

Allocability

Generate a Detail Trial Balance, as of today. Analyze all entries (budgets & expenditures) on the DTB, and make sure that every entry made after the "End Date" of the project:

Indirect Cost Calculation

Ensure on the Project Budget Status (BBA) report that the Indirect Cost (IDC) are calculated correctly. Consider the following:

If not correct, make a Journal Entry (JE) to adjust it.

Revenues Must Equal Expenses

Ensure on the Project Budget Status (BBA) report that the Total Grant Revenues equal Total Expenses. If not, adjust revenues with a Journal Entry.

Note: Adjusting IDC and the Revenue could be done through one JE.

First Update Project Budget Status Report

Closing Journal Entry

Make the CLOSING JE to close the available balances on the BBA Report (i.e. reversing all available balances on the BBA report, which would reduce the Budget figures to Actual Expenditures).

Mark Project as Closed in the Contract Folder (Blue Folder)

Second Update Project Budget Status Report

Again, update the Project Budget Status (BBA) reports (both GC 01 & GC 09). At this point, the available balances on the BBA reports will be all zero & "Total Budget" will be equal to Total Expenditure.

Mark Project as Closed in PeopleSoft/Oracle

Access the "Award Attributes" page of the project In PeopleSoft/Oracle

Mark Project as Closed in the Billing Schedule

On the BILLING SCHEDULE spreadsheet:

Final Review Accounts Receivable

Ensure the balance on the AR Report is zero, and we are not expecting to receive any more payments:

Notification of PeopleSoft Administration

As a final step, log a case with EB Suite to the PeopleSoft Administrators asking them to close the project. This step completely closes the project and will take it off the PeopleSoft system. Thereafter, no entries towards the project will be possible.

Additional Steps For the Closing of Federal Projects

National Institutes of Health (NIH)

File the "Financial Status Report" (FSR) at the end of the project electronically through the NIH Commons website.

Additional information on electronic submission of an FSR is available at commons@od.nih.gov or Tel # 866-504-9552.

Important Note: Most of the new NIH Grants have the SNAP Clause: "This grant is subject to Streamlined Noncompeting Award Procedures (SNAP)". In this case, there is no need to file a FSR each year. A FSR will be due 90 days after the Final Budget Period ends.

T:\USER\Contracts\GROUP\Sponsored Projects\ FED YEAR END WK'S, LETTER\S, & FORMS\ITD Worksheets

National Science Foundation (NSF)

There are no additional requirements (reports, etc.) for NSF grants.

U.S. Department of Education

For U.S. Department of Education grants Form 269, "Financial Status Report", short form, needs to be filed on an annual basis.

Update Excel Spreadsheet

T:\USER\Contracts\GROUP\Sponsored Projects\ FED YEAR END WK'S, LETTERES, & FORMS\ITD Worksheets

Prepare Form 269 - Short Form

T:\USER\Contracts\GROUP\Sponsored Projects\Cash Requests & Reports\PDF Forms\Reports

Prepare Cover Letter

T:\USER\Contracts\GROUP\Sponsored Projects\FED YEAR END WK'S, LETTERS, & FORMS\Letters