Rolling Outage Schedule

Campus Network Refresh Project

The Campus Network Refresh Project is now complete.

 

For more information about the completed work listed on this page, view the network refresh project contact list.

Location Area Impacted Outage Date Outage Time Status
Sagebrush Hall All of Sagebrush Hall Tue 6/17/08 5:00 am to 7:00 am Completed
Jacaranda Hall – Johnson Auditorium Johnson Auditorium Tue 6/17/08 8:00 am to 9:00 am Completed
HHD Preschool All of HHD Preschool & the Black House Tue 6/17/08 9:00 am to 10:00 am Completed
Monterey Hall All of Monterey Hall & University Club Wed 6/18/08 5:00 am to 7:00 am Completed
Monterey Hall All of Monterey Hall 3rd Floor Wed 6/18/08 8:00 am to 10:00 am Completed
Monterey Hall All of Monterey Hall 2nd Floor Wed 6/18/08 10:00 am to 11:00 am Completed
Monterey Hall All of Monterey Hall 2nd Floor Wed 6/18/08 11:00 am to 12:00 pm Completed
Oviatt Library Oviatt Server Room Thu 6/19/08 8:00 am to 9:00 am Completed
Oviatt Library Oviatt Library 2nd Floor West Wing Thu 6/19/08 9:00 am to 10:00 am Completed
Oviatt Library Oviatt Library 2nd Floor Core Section Thu 6/19/08 10:00 am to 11:00 am Completed
Oviatt Library Oviatt 3rd Floor Core Section Thu 6/19/08 11:00 am to 12:00 pm Completed
Oviatt Library Oviatt Library 4th Floor Core Section Thu 6/19/08 1:00 pm to 2:00 pm Completed
Oviatt Library Oviatt 4th Floor East Wing (Rm 447) Thu 6/19/08 2:00 pm to 3:00 pm Completed
Health Center Health Center, Green House, Satellite Central Plant PPM (formerly Boiler Room), Science 5 construction Fri 6/20/08 5:00 am to 7:00 am Completed
Green House All of Green House and the Satellite Central Plant PPM (formerly Boiler Room) Fri 6/20/08 8:00 am to 9:00 am Completed
Satellite Central Plant PPM (formerly Boiler Room) All of the Satellite Central Plant PPM (formerly Boiler Room) Fri 6/20/08 9:00 am to 10:00 am Completed
Physical Plant Mgmt PPM Auto Shop/Ground Bldg (Rm 300's) Fri 6/20/08 10:00 am to 11:00 am Completed
Physical Plant Mgmt PPM Central Plant Building Fri 6/20/08 11:00 am to 12:00 pm Completed
Physical Plant Mgmt PPM Mail Room/Receiving, ReproGraphics, and EHS (Rm 200's), Hazmat Fri 6/20/08 1:00 pm to 3:00 pm Completed
Physical Plant Mgmt PPM Stock Room, Electric Shop, and Plumbing Shop Fri 6/20/08 3:00 pm to 4:00 pm Completed
Physical Plant Mgmt PPM Carpenter Shop, Paint Shop, Stock Room, Electric Shop,
Plumbing Shop, and Waste Storage Building
Fri 6/20/08 4:00 pm to 5:00 pm Completed
Sequoia Hall All of Sequoia Hall Sat 6/21/08 12:00 am to 2:00 am Completed
Sierra Hall All of Sierra Hall and Sierra Center Mon 6/23/08 5:00 am to 7:00 am Completed
Sierra Hall All of Sierra Hall and Sierra Center Mon 6/23/08 5:00 am to 7:00 am Completed
Sierra Hall Sierra Hall 4th Floor Mon 6/23/08 8:00 am to 10:00 am Completed
Sierra Hall Sierra Hall 3rd Floor Mon 6/23/08 8:00 am to 10:00 am Completed
Sierra Hall Sierra Hall 1st Floor Mon 6/23/08 11:00 am to 1:00 pm Completed
UPA – 14 Building 14 Offices Mon 6/23/08 11:00 am to 1:00 pm Completed
USU BDF All of USU Tue 6/24/08 5:00 am to 7:00 am Completed
Black House All of Black House Tue 6/24/08 8:00 am to 9:00 am Completed
Citrus Hall Planetarium Citrus Hall Planetarium Tue 6/24/08 8:00 am to 9:00 am Completed
ROTC Trailer ROTC Trailer Tue 6/24/08 9:00 am to 10:00 am Completed
University Hall – Trailer University Hall Trailer Tue 6/24/08 9:00 am to 11:00 am Completed
DPS/Structure/B3 DPS B3 Structure Tue 6/24/08 10:00 am to 11:00 am Completed
MDF MDF Tue 6/24/08 12:00 pm to 2:00 pm Completed
Manzanita Hall All of Mazanita Hall Wed 6/25/08 5:00 am to 7:00 am Completed
Manzanita Hall Mazanita Hall 2nd Floor Office North (Rooms 200–240's) Wed 6/25/08 8:00 am to 10:00 am Completed
Manzanita Hall Mazanita 3rd Floor Wed 6/25/08 8:00 am to 10:00 am Completed
Manzanita Hall Mazanita Hall The Armer Theater Wed 6/25/08 10:00 am to 11:00 am Completed
Manzanita Hall Mazanita 1st Floor South Side (Rooms 150+) Wed 6/25/08 10:00 am to 12:00 pm Completed
Manzanita Hall Mazanita 2nd Floor South Side (Rooms 250+) Wed 6/25/08 1:00 pm to 3:00 pm Completed
School of Education All of Education Including Education Administration Thu 6/26/08 5:00 am to 7:00 am Completed
School of Education Faculty Offices, Dean's Office, Classrooms, Labs on 1st, 2nd and 3rd Floors on East Side of South Building Thu 6/26/08 7:00 am to 9:00 am Completed
School of Education 1st, 2nd, and 3rd Floors Southwest Thu 6/26/08 8:00 am to 10:00 am Completed
School of Education Education Administration Thu 6/26/08 9:00 am to 11:00 am Completed
School of Education Education 1st and 2nd Floors Northwest End (Rooms 1200's and 2200's) Thu 6/26/08 12:00 pm to 2:00 pm Completed
Art Design Center Art Design Center Buildings 4 and 6, Classrooms, Labs and Office in Rooms 400's and 600's Mon 6/30/08 5:00 am to 7:00 am Completed
Art Design Center Art Design Center Classrooms, Offices in Rooms 200's and the Art Gallery Mon 6/30/08 7:00 am to 8:00 am Completed
Art Design Center Art Design Building 1 Department Office Mon 6/30/08 7:00 am to 8:00 am Completed
Bank Bldg All of the Bank Building Mon 6/30/08 8:00 am to 9:00 am Completed
Chicano House All of Chicano House Mon 6/30/08 8:00 am to 9:00 am Completed
Redwood Hall All of Redwood Hall Tue 7/1/08 5:00 am to 7:00 am Completed
Redwood Hall Redwood Hall 2nd Floor Offices West Side Tue 7/1/08 8:00 am to 10:00 am Completed
Redwood Hall Redwood Hall 1st Floor South Side Tue 7/1/08 10:00 am to 11:00 am Completed
Redwood Hall Redwood Hall Addition 2nd Floor Offices East Side Tue 7/1/08 12:00 pm to 1:00 pm Completed
Redwood Hall Redwood Hall – South Offices / Rooms Tue 7/1/08 12:00 pm to 1:00 pm Completed
Redwood Hall All of Intercollegiate Office Tue 7/1/08 1:00 pm to 2:00 pm Completed
Redwood Hall Intramural Office Tue 7/1/08 1:00 pm to 2:00 pm Completed
Juniper Hall Juniper Hall Classrooms, Labs and Offices on the 1st and 2nd Floors of the Northwest Quadrant Thu 7/24/08 1:00 pm to 3:00 pm Completed
Juniper Hall Juniper Hall Classroom, Labs and Offices on the 1st and 2nd Floors of the Northeast Quadrant Thu 7/24/08 3:00 pm to 5:00 pm Completed
Juniper Hall All of Juniper Hall Fri 7/25/08 5:00 am to 7:00 am Completed
Juniper Hall Juniper Hall Classrooms and Labs on the 1st and 2nd Floors on the South End plus Offices on the 3rd Floor of the Northeast Quadrant Fri 7/25/08 7:00 am to 9:00 am Completed
Juniper Hall Juniper Hall Classroom, Labs, and Offices on the 1st and 2nd Floors of the Southwest Quadrant Fri 7/25/08 8:00 am to 10:00 am Completed
Juniper Hall Juniper Hall Offices on the 3rd and 4th Floors Northwest Quadrant Fri 7/25/08 10:00 am to 12:00 pm Completed
Juniper Hall Juniper Hall Offices on the 3rd and 4th Floors Northeast Quadrant Fri 7/25/08 10:00 am to 12:00 pm Completed
Juniper Hall Juniper Hall Offices on the 3rd and 4th Floors Southeast Quadrant Fri 7/25/08 12:00 pm to 2:00 pm Completed
Juniper Hall Juniper Hall on the 3rd and 4th Floors Offices, Southwest Quadrant Fri 7/25/08 1:00 pm to 3:00 pm Completed
Juniper Hall Noski Auditorium Fri 7/25/08 3:00 pm to 4:00 pm Completed